Issued: 17 December 2019
RESTORING TODDBROOK RESERVOIR
Update on Repair Project – Work to start in January
The Canal & River Trust announced today (17 December) the first steps in the restoration of Toddbrook Reservoir. Early in the new year the charity will start a project to enhance the resilience of the dam wall and spillway following damage to the latter back in August after heavy rainfall.
The works to the dam will be followed later in 2020 by improvements to the Todd Brook inlet channel at the head of the reservoir. This will provide greater control over how much water flows from the brook into the reservoir or around the reservoir via a bypass channel. This project will take the opportunity to include the installation of a new footbridge across the brook to create a safe route for people wishing to walk from one side of the valley to the other.
The Canal & River Trust, which cares for Toddbrook Reservoir and 2,000 miles of waterways across England & Wales, is working closely with contractors Kier to keep the reservoir drained as preparations are made for its long-term repair – a process that is likely to take several years and cost around £10 million.
Works to the dam wall and auxiliary spillway
Starting on Monday 6 January 2020, temporary works will be carried out on the dam’s auxiliary spillway, which was damaged back in the summer. A protective, waterproof nib (short wall) will be inserted all along the spillway crest which will reach down into the dam’s clay core.
The spillway crest will be increased in height by just over one metre at either end and sturdy concrete waterproof barriers will be installed on the spillway slope to channel any overflowing water into the central undamaged section – which will be lined for extra protection.
The new features will ensure that the dam is secure in any extreme weather events. They will remain in place until permanent reconstruction of the dam is undertaken.
Improving the Todd Brook inlet and bypass channel
Toddbrook Reservoir is fed by a stream, Todd Brook, which is diverted at the head of the reservoir to either feed into the reservoir or along a bypass channel. The bypass channel runs along the North West edge of the reservoir before feeding directly into the River Goyt.
After the emergency in August, the masonry weir at the inlet channel was raised with the installation of mesh baskets filled with sandbags. In the year ahead, these will be replaced by a footbridge incorporating sluice gates, to provide a higher degree of control over water flows.
The Trust will continue to monitor the bypass channel closely, with expert hydrologists having carried out extensive modelling to assess the topography and the maximum capacity at all points along its course. During normal weather conditions, while the reservoir remains drained, all flow is sent down the bypass channel i.e. none into the reservoir.
Long term plan and inquiry update
The Trust has commissioned an independent inquiry into what caused the damage to the dam’s auxiliary spillway. It is also assisting with an independent review commissioned by government. Both these reports are due to be published early in 2020 and will guide the long-term repair of the dam.
Simon Bamford, asset improvement director for the Canal & River Trust, explains: “We are keen to hear the findings of the independent inquiries so we can move forward and decide how best to fix the dam for the long term. Once we know what caused the damage to the dam we will be able to work out a detailed plan for repairing it, including a precise timetable and costings. In the meantime, we will be doing some work to protect the reservoir and further improve its resilience against any extreme weather events.
“At the head of the reservoir, we know a footbridge has been on the wish list of some local residents, so we are delighted we can incorporate this into the design for improving the inlet.”
Fish rescue
During the final week before Christmas, a third fish rescue is taking place (weather permitting) to net as many of the remaining fish as possible before the reservoir is drained down even further. This follows fish rescues in August and October when thousands of coarse fish, such as bream, roach, perch and pike, were captured in large nets and then transported to another Trust reservoir near Birmingham which has been in a good position to re-home such large numbers of fish. In total it is estimated that about 30,000 fish (5 tonnes) will have been rehomed.
Residents’ briefing
Residents are invited to hear about the planned interim repair works at two briefings to be held this evening (Tuesday 17 December) at the Palace Hotel in Buxton at 6pm and 7.30pm.
Julie Sharman, chief operating officer with the Canal & River Trust, explained: “With work due to start in January, the Trust is keen to keep residents updated with the latest information. We apologise that people are having to travel to Buxton for the briefing but finding a suitable venue with sufficient capacity has been a challenge in the week before Christmas.
“We have already met many local residents at four public open days in October and at the weekly surgery drop-in sessions in Whaley Bridge, but we look forward to updating a wider audience with the latest news. More public open days are planned for the spring and we will be sending a newsletter to more than 3,000 Whaley Bridge homes to explain about the repair works.”
No booking is required for the briefings to be held at the Palace Hotel, Palace Road, Buxton, SK17 6AG, opposite Buxton Train Station. Just turn up at 6pm or 7.30pm. Anyone needing more information can check out the Trust’s website www.canalrivertrust.org.uk/restoring-toddbrook-reservoir or email toddbrook@canalrivertrust.org.uk.
ENDS
Comments are closed.